DFDC The Hague - UPS-C Maintenance
Completed Maintenance
Scheduled on 08/09/2025 05:00:00
Estimated finish 08/09/2025 10:00:00
As part of our ongoing infrastructure development plan, one of our UPS clusters—originally commissioned in November 2024 during the early stages of our expansion—will be migrated to a newly prepared power path, Feed C, on Saturday, August 9, 2025.
Feed C is the fourth and final fully diverse power path (A, B, C, D) in our design, completing the last phase of power-related infrastructure upgrades. This enhancement is a key step toward increasing overall system redundancy and preparing the facility for upcoming infrastructure certification.
Planned Work Details
Impact:
- No service (or any form of power) interruption is anticipated
- Affected customers will temporarily lose UPS protection during the migration.
- Customers with dual power feeds connected to other UPS clusters will remain fully protected.
Affected Rows:
- ZA.C1.BB02 (Row 1, bus bar 2) – Racks ZA.C1.R1 - ZA.C1.R15
- ZA.C3.BB03 (Row 3, bus bar 3) – Racks ZA.C3.R1 - ZA.C3.R15
- ZA.C5.BB02 (Row 5, bus bar 2) – Racks ZA.C5.R1 - ZA.C5.R15
- ZA.C6.BB03 (Row 6, bus bar 3) – Racks ZA.C6.R5 - ZA.C6.R8
- ZA.C7.BB02 (Row 7, bus bar 2) – Racks ZA.C7.R1 - ZA.C7.R15
Maintenance Schedule (CEST)
07:00 – Engage external bypass and transfer load to unprotected utility power
08:30 – Migrate UPS input and power panel to new Power Feed C
11:00 – Return load through UPS, perform load verification, battery checks, and confirm system status
12:00 – Close maintenance window
On-Site Access & Coordination
We recommend minimizing on-site activity during this maintenance period. Customers requiring on-site engineering support are advised to coordinate with our operations team in advance to ensure safe access and proper support during the scheduled work.
We appreciate your cooperation as we continue to invest in the resilience and reliability of our facility.
Related servers / services:
UPS-C - The Hague Data Center
Date |
Action |
08/09/2025 08:20:00 |
Maintenance still in progress. Expected new maintenance end time 16:00 Netherlands local time |
08/09/2025 11:35:00 |
Successfully completed |